By Robert Barone, RA, LEED AP, Director, Institutional Construction Services | Partner Engineering and Science, Inc.
Originally Published in the 2025 CLRM Journal
The construction industry is inherently complex, but some projects pose significantly higher risks due to their scale, design intricacies, stakeholder involvement, and financing structures. Among these, full-service high-rise hotels—especially those carrying a prestigious independent or corporate flag—stand out as particularly challenging. These projects require meticulous planning and risk mitigation strategies to ensure successful completion.
High-risk construction projects generally involve multiple layers of complexity, including:
Multiple Stakeholders: Unlike a typical commercial building with a single owner and contractor, high-rise hotels involve developers, contractors, lenders, equity investors, and hotel operators (flags). Each party has its own priorities and influence on the project, which can lead to conflicts and unexpected delays. Additionally, third-party operators—such as high-end restaurants, spas, and entertainment venues—may impose their own design and financial requirements.
Evolving Designs: Unlike office buildings or multifamily units, where core designs are typically finalized before construction, hotel projects often commence with incomplete public space and amenity designs. A common scenario is when the guest rooms are approved early, but the design of ballrooms, spas, and other public areas is left unfinished until later stages. This phased approach helps capture the latest market trends but also increases project risks, as delays in these areas can have ripple effects on the construction timeline.
Stringent Brand Standards: Luxury hotel flags, such as Four Seasons or Mandarin Oriental, impose strict brand guidelines that can evolve during construction, requiring adjustments to design, materials, and FF&E (Furniture, Fixtures & Equipment). A developer may begin construction with one approved set of standards only to face flag updates mid-project, requiring costly redesigns and procurement adjustments.
Long Lead Items and Procurement Challenges: Specialty materials, high-end finishes, and imported items often require extensive lead times and large upfront deposits, making procurement timing critical. If designs are not finalized early enough, developers may struggle to secure key elements—such as imported marble, custom furniture, and specialty lighting—in time to meet the original construction schedule.
Project Timeline Sensitivities: A high-rise luxury hotel can take 30 to 36 months to complete, and delayed approvals or unexpected design changes can significantly impact budgets and delivery dates. Because hotels rely on revenue-generating public spaces to enhance profitability, delays in these areas can reduce projected revenue streams.
To successfully navigate high-risk construction projects, lenders, investors, and developers must implement structured risk management approaches. Below are some essential strategies for investors and lenders:
In addition to a thorough Document and Cost Review, investors and lenders should ensure that the following key project elements are thoroughly vetted before financing is secured:
Once construction begins, rigorous oversight is required to track project development:
During the construction of a luxury hotel in Florida, the hotel operator (flag) introduced updated brand standards requiring modifications to plumbing and guest room fixtures. By the time these changes were communicated, plumbing rough-ins had already been completed, forcing the developer to redo portions of the work. The rework not only caused delays but also added significant costs to the budget. Because the developer had agreed to meet the operator’s most current standards, they were contractually obligated to cover these costs. Additionally, long-lead items such as imported materials and custom furniture had already been procured based on previous specifications, further complicating the integration of the changes. This case underscores the importance of proactive communication and well-defined agreements. Establishing timelines for design approvals and outlining cost-sharing responsibilities for late-stage changes can prevent disputes and mitigate the impact of unforeseen costs and adjustments.
*******
Navigating high-risk construction projects—particularly luxury high-rise hotels—requires a proactive approach to planning, monitoring, and stakeholder coordination. Lenders and investors must establish clear expectations before closing the loan, track milestones diligently, and anticipate the financial implications of design evolutions. By implementing robust risk management practices, they can ensure that these ambitious projects reach completion on time and within budget, ultimately maximizing return on investment while minimizing exposure to costly setbacks.