By Christina Fanning, Technical Director, Construction Services | Partner Engineering and Science, Inc.
Originally published in the 2026 CLRM Journal.

Construction projects rarely fail at one defining moment. More often, failure begins quietly through small inconsistencies, overlooked details, or decisions made early in the process that don’t reveal their consequences until months later. When a lender receives a request for additional funding, a contractor replacement, or a loan extension, the problems often feel sudden. In reality, distress signals have usually been visible for quite some time.
The challenge is that early warning signs don’t announce themselves as crises. Instead, they appear as manageable issues: a few change orders, a slower-than-expected ramp-up of labor, a schedule that slips but is expected to “catch up.” Viewed in isolation, none of these signals is alarming. Viewed together, they often tell a very different story.
Having spent years reviewing active construction projects at every stage of progress, certain patterns consistently emerge as precursor indicators that a project might be headed toward trouble. Understanding not just what those indicators are, but what they mean, is essential for lenders, investors, and owners trying to protect a project from becoming distressed.
Many consequential construction problems begin on a project before the first wrecking ball is swung, the first shovel is dug into the ground, or the first nail is hammered in place. One of the earliest indicators is misalignment between the construction contract and the drawings. When a contract is executed based on earlier sets of plans rather than the current sets, which happens when drawings advance through permitting and detailing phases after a contractor has bid and a contract has formed, the contract no longer reflects the true scope of work. Drawings change for many reasons, including code requirements, constructability issues, and comments from jurisdictional authorities, and those changes almost always come with cost implications. Furthermore, when pricing and contract negotiations precede final design, which occurs more often than it should, change orders are inevitable.
Allowances can be another early signal worth examining closely, not because they are inherently problematic, but because they indicate where information was incomplete at the time of contracting. An allowance typically means a scope of work was not detailed enough to price or that there was insufficient information to establish a hard cost amount. While allowances are typically reconciled during the course of construction, sometimes higher and sometimes lower, they represent areas of the project where exposure to cost fluctuations is high. The more allowances embedded in a contract budget, particularly for significant scopes of work, the more assumptions the contractor makes and the greater the likelihood that those assumptions will be tested once construction is underway. Additionally, allowances allocated to late construction activities, such as landscaping, can be targets for reduction or even depletion when there are demands for additional funds earlier on in the project, leaving the project with much less curb appeal than depicted in marketed architectural renderings.
Gaps in due diligence further compound uncertainty by deferring risks rather than removing them. When certain due diligence items are waived, incomplete, or unavailable at the time of underwriting, the project proceeds based on assumptions about existing conditions. When geotechnical due diligence is shortchanged, for example, and excavation encounters rock, unsuitable soils, or groundwater conditions that were never fully evaluated or priced, the scope of work changes and costs increase. Such risks don’t suddenly appear once construction begins; they were always there, just not identified or priced. Unexpected changes can affect more than just cost, as sequencing, schedule, and the type of labor or equipment are often impacted. Unforeseen conditions are not unusual in construction, but when they are not discovered because of gaps in due diligence, or discovered without contingency planning, they can quickly consume both budget and time.
The contractor’s familiarity with the local jurisdiction also plays an important role early in a project. Permitting and inspection requirements can vary significantly between jurisdictions and not just in form, but in sequencing and execution expectations. A contractor unfamiliar with local processes may technically be qualified to perform the work, yet still underestimate the time and coordination required to move through approvals and inspections. These issues often surface early, sometimes before vertical construction begins in new builds, and can quietly slow project momentum when the project schedule assumes a level of procedural familiarity that the team does not have.
One or more of these conditions doesn’t guarantee a project will experience trouble, but each one puts stress on a project, and the accumulation of stress increases the likelihood that a project will encounter trouble.
Once construction begins, labor is often the earliest and most visible indicator that something isn’t going according to plan. Construction follows a predictable rhythm. Early phases may require limited manpower, but as the structure takes shape and more trades are needed onsite, labor should ramp up accordingly. When that ramp-up doesn’t occur, or when crews appear inconsistently, it raises questions that extend beyond simple scheduling matters. For new building construction, a noticeable increase in manpower is expected when the project is framed and enclosed, as multiple other trades should be ready to begin interior work. If there is not a noticeable increase in manpower, that could signal labor issues.
In some cases, labor shortages stem from market conditions or a lack of skilled trades. In others, the cause is financial. When subcontractors are not being paid reliably, whether due to cash-flow constraints at the general contractor level or delays in funding upstream, staffing a project with tradesmen can become inconsistent. In certain regions, workforce disruptions related to immigration enforcement can create sudden labor gaps, forcing contractors to slow work or re-sequence activities while seeking to secure replacement crews.
In circumstances where labor is compromised, what matters most is not simply that manpower is light, but why. Labor issues are rarely isolated. They are often connected to the timing of subcontractor buyouts, subcontractor stability, cash flow constraints, or broader coordination challenges. When labor slows, progress slows, and the project schedule begins to feel the impact.
If labor is often the first visible signal of project trouble, the schedule is where multiple indicators intersect. A realistic construction schedule should accurately reflect all of the items necessary to successfully complete the project: procurement milestones for subcontractors and materials, equipment logistics, jurisdictional activities, and work activities defined enough to allow for proper monitoring, as well as the logic, sequencing, and equipment and manpower needs of the entire project. The complexity of how all these items affect each other helps determine whether work activities can overlap or must occur in sequence. Forensic studies of troubled projects often reveal that problems could have been predicted by, and were the result of, unrealistic construction schedules. As project conditions change, the schedule must incorporate relevant changes and should evolve accordingly.
When schedules are not updated, or when updates no longer align with what is happening on site, it becomes difficult to distinguish optimism from reality. In many cases, the absence of an updated schedule does not simply reflect delay in a project’s progress; it reflects a lack of analysis around how the delay affects the remaining path to completion.
Schedule slippage has consequences that extend beyond just the simple progress of physical construction. Interest reserves are sized based on projected duration, so delays impact reserve analysis. Loan maturities, SBA guarantees, and operational timelines all rely on realistic completion dates as well, so when schedules quietly slip without acknowledgment, financial pressure can rapidly accumulate in the background.
Delays themselves are not unusual. What becomes problematic is the lack of transparency around them. A schedule that is not being actively managed is often a sign that the project team does not have a clear or achievable path forward. Schedule uncertainty tends to surface first in financing matters, sometimes well before the impact can be seen in the progress of the physical construction.
Change orders are frequently viewed as a budget issue, but they also can provide insight into a project’s underlying health. Some change orders are legitimate responses to unforeseen conditions or owner-driven modifications. Others trace back to incomplete drawings, insufficient detailing, or scope gaps that existed before construction began. When change orders appear early and often, they tend to reflect decisions made upstream, such as contracts executed before documents were fully aligned, or scopes priced before they were clearly defined. In that sense, change orders are often the point at which earlier assumptions are formally reconciled.
Contractors typically know early whether a project is trending toward profitability or loss. When margins begin to erode, behavior changes. RFIs increase, scope interpretations tighten, documentation becomes more formal, and billing becomes more assertive. These responses are not unusual in construction, but they can accelerate cost and schedule pressure if the root causes are not addressed. Excessive change orders don’t just strain contingency; they strain coordination and trust across the entire project team: lender, borrower, and contractor.
Buyouts are one of the most underappreciated components of construction risk. A buyout is not just awarding a contract; it is the moment when the project’s budget meets market reality. When subcontract agreements exceed the budget line items allocated to them, don’t align with the Schedule of Values, or scope buyouts remain incomplete well into construction, financial gaps begin to form. These gaps may not be immediately visible in monthly reporting, but they eventually surface through delayed work, funding reallocations, or excessive usage of remaining contingency.
In some cases, owner involvement influences this process. Owner participation in construction is not inherently problematic and is often beneficial. However, when owners modify procurement strategies, override subcontractor selections to reduce cost, or direct changes to sequencing in an effort to accelerate progress without understanding the risks that come with these actions, they may inadvertently cause negative pressures, as the assumptions underlying the original schedule and budget may no longer be valid. These changes may unintentionally disrupt buyouts, destabilize labor planning, or introduce coordination challenges that the project team never planned for. When this occurs, increased risk is introduced not from the owner’s involvement itself, but from the misalignment it creates between budget, schedule, and execution.
Compliance issues tend to appear later in construction, but they rarely arrive without warning. Stop-work orders often result from inspections being missed, permitting miscues, or work being performed out of sequence. In some cases, they stem from local requirements discussed earlier. In others, they arise when schedule or financial pressures push teams to move faster than the project can support. Out-of-sequence work may be performed, such as installing finishes before life-safety systems are active, or advancing work before required approvals are in place, which further exacerbates the problem instead of relieving it. A stop-work order does more than halt progress; it often forces rework, creates storage and logistics challenges, and disrupts trade sequencing. These impacts tend to cascade through the remainder of the project.
For projects in trouble, lenders often request that their trusted due diligence providers perform a Cost-to-Complete (CTC) report on a project. By the time a lender requests a CTC report, a project has often reached a point of distress where previous positive assumptions are no longer valid and more drastic actions are needed. Schedules may have slipped, contingencies might be strained, or circumstances could have changed so materially that a contractor replacement is being considered, a refinancing is underway, or the original construction duration has been exceeded. At this stage, a deep dive by a trusted consultant may be needed in order to provide essential clarity.
A meaningful Cost-to-Complete analysis looks beyond just the percentage complete of line items. It evaluates whether remaining funds can realistically support the work left to be done, given the current subcontract commitments, the schedule status, the amount of stored materials, and any additional general conditions that might be required. In many cases, the CTC represents the first clear view of the project as it actually exists, rather than how it was originally envisioned.
What is often overlooked is that projects rarely arrive at this point without warning. Labor instability, schedule drift, misaligned buyouts, recurring and/or excessive change orders, and compliance challenges tend to surface well before a CTC is contemplated. Individually, these issues often appear manageable, but together they reduce flexibility in managing the project, adding stress on multiple fronts and signaling that risk is accumulating.
Construction risk management helps mitigate risk, but it cannot eliminate all uncertainty, nor is it always perfectly accurate in predicting project failures. The value of good construction risk management lies in improving visibility across the life of a project, whether oversight is managed internally or supported by experienced third-party consultants. Early document and cost reviews, contractor evaluation, progress monitoring, and funds control services during construction help identify emerging issues while there is still an ability to redress and adjust course.
Construction projects rarely fail because of a single, unexpected event. They move toward distress when signals of trouble are normalized, deferred, or explained away. The difference between a project that course-corrects and one that continues down a course of distress is often timing, or lack thereof, of intervention steps. When issues are recognized and acknowledged early, and intervening actions are taken, there is room to safely manage a project to successful completion. If the opposite occurs, project participants should anticipate increased management challenges as the road to success becomes more complex.
