Construction Progress Monitoring

Construction lenders often require us to be their boots on the ground and report on the progress of a project. With Construction Progress Monitoring, Partner will conduct regular or monthly construction progress site assessments to ensure that the proposed improvements at the subject site are progressing as required in the contract/agreement. Partner will confirm information provided by the client and assess the status of the project, the construction operations, and the status of the collateral. Partner’s assessor will visit the site as directed or on a pre-arranged schedule and prepare a written report to determine if the required improvements have been completed and are in compliance with the client’s scope of work.

What's Involved

While on site, Partner’s inspector will conduct, at a minimum, the following reviews:

  • Observe the construction work and establish its level of completion.
  • Assess general conformance with the bank’s understanding of the GC Contract.
  • Assess the adequacy of material and workmanship.
  • Verify conformance with the provisions of the construction loan agreement.
  • Verify the adequacy of the contractor’s application for payment.
  • Identify and report construction changes and potential and pending change orders.
  • Identify and report status of stored materials and if requested, off-site materials.
  • Assess the conformance to the construction schedule.
  • Verify quality control measures by applicable agencies, architect and engineers, material testing laboratories, and qualified construction inspectors.
  • Assess adequacy of the labor on site, and address any potential work hindrances or stoppage.
  • If requested, evaluate sufficiency of funds remaining to complete the project and provide recommendations as appropriate.
  • Confirm that all major contract applications for payment invoices are accompanied by a current conditional and unconditional lien release.

Related Insights

Frequently Asked Questions

Report it to the project manager immediately so that they can investigate and take corrective action to keep the project on track.

Tools can include drones for aerial monitoring, project management software for tracking tasks and timelines, GPS tracking for equipment and materials, and sensors for monitoring environmental conditions.

Manual Data Entry: Time-consuming and prone to errors.
Communication Gaps: Inconsistent information flow between stakeholders.
Data Analysis: Difficulty in interpreting vast amounts of collected data.

Monitoring frequency can vary depending on the size and complexity of the project, but typically it’s done weekly or bi-weekly to ensure that any issues are addressed promptly.

Let us be your Partner

Learn how we can support your next project or share insights via our newsletter.
Terms and Conditions  |  Privacy Policy   |  Website Terms of Use  |  © 2023 Partner ESI. All rights reserved.
crossmenuchevron-uparrow-uparrow-rightchevron-right-circle linkedin facebook pinterest youtube rss twitter instagram facebook-blank rss-blank linkedin-blank pinterest youtube twitter instagram